Article Content
PROJECT DETAIL
Investor: HAI LONG HUNG YEN JOINT STOCK COMPANY
Main contractor: PHUC TRUONG HAI BOILER CO., LTD
Location: Xuan Dao Hamlet, Xuan Duc Commune, My Hao Town, Hung Yen Province.
Design capacity: 6 Tons/h (6,000 Kg/h)
Expected Completion time: 70 working days
Design pressure: 12 Bar
Durable test pressure: 18 Bar
Maximum working pressure: 8 Bar
PTH Boiler provides the boiler capacity of 6 ton/h for Hai Long-Hung Yen brewery. This project marks a long-term cooperation between Phuc Truong Hai Boiler and Hai Long Hung Yen Joint Stock Company.
PTH Boiler achieved the expected completion in 70 working days, based on more than 10 years of experience operating in the field of manufacturing and installing boilers.
Related Articles